Whittaker

Offshore + Marine Engineering

Walk to Work

Walk to Work

During September and October 2015 Whittaker successfully managed a Walk to Work campaign for a client in the North Sea.

Transfers were scheduled to be carried out twice daily, one at 7am and again at 7pm.

During the 27 days that the vessel was in position a total of 51 transfers out of a possible 54 were completed.

The total number of personnel transferred during the period was 3663 which amounted to 22,440 man hours.

Whittaker supplied a wide range of construction trades for the duration of the W2W campaign.  The 27 day campaign was key to first oil delivery.

Whittaker supplied the following trades:-

Offshore Construction Supervisor

Welders

Platers

Riggers

Scaffolders

Mechanics

Electricians

Medic

W2W Co-ordinators